Long Hill Rd Closing and Route 6 Resurfacing
Road Closure Notice – Long Hill Road
For all those affected by the Long Hill Rd. detour:
Due to extended emergency response times while the road is closed, please provide dispatchers with all pertinent information when calling 911. This includes any relevant medical details and situational information.
Providing accurate and complete information will help ensure the appropriate level of response urgency.
Thank you for your cooperation,
Ron Mike
Fire Chief
Beginning May 13, 2026, Long Hill Road will be closed at the Hop River to allow for a bridge replacement project. This closure is expected to remain in effect through approximately December 2026.
Motorists are advised to plan alternate routes and allow for additional travel time. Please follow posted detours and exercise caution when traveling in the area.
We appreciate your patience and cooperation during this necessary infrastructure improvement.
Milling and Resurfacing on Route 6 in Bolton Coventry and Andover
4/13/2026
The Connecticut Department of Transportation (CTDOT) is announcing that a milling and resurfacing project will be performed on Route 6 in Bolton, Coventry and Andover. This project is scheduled to occur on Sunday, April 19 and be completed on Monday, June 29, 2026. The project DOT01710531CN F & H consists of milling and resurfacing a 5.83 -mile segment of Route 6 in Bolton, Coventry and Andover from 0.02 miles east of the east bound and west bound connector for Route 6 to 0.06 Miles west of Bunker Hill Road and the commuter lot next to the Andover Post Office. This project is scheduled to begin milling by Rafferty Fine Grading on Sunday, April 19 to Tuesday, May 12, 2026. The resurfacing segment of this project by Tilcon Connecticut anticipated to begin on Sunday, May 17 to Monday, June 29, 2026. This project is included in CTDOT’s 2026 Vendor Resurfacing Program.
LANE CLOSURE/DETOUR INFO
Motorists can expect lane closures of Route 6 in Bolton, Coventry and Andover from 0.02 Miles east of the east bound and west bound connector Route 6 to 0.06 miles west of Bunker Hill Road and limited access to the Commuter lot next to the Andover Post Office. Traffic control personnel and signing patterns will guide motorists through the work zone. The work schedule for this project is from 07:00 p.m. to 05:00 a.m., Sunday to Thursday.
Motorists should be aware that modifications or extensions to this schedule may become necessary due to weather delays or other unforeseen conditions. Motorists are advised to maintain a safe speed when driving in this area.
Media Contact:
860-594-2560
[email protected]
Operating Hours: Monday - Friday 8:00 a.m. to 4:30 p.m.
https://portal.ct.gov/dot/ctdot-construction-advisories/2026/milling-and...